ROVENNA

Controlled rock demolition project on Lake Como

ROVENNA

In the setting of Lake Como, we carried out a controlled demolition of a rock outcrop as a preliminary step for the construction of a new underground swimming pool and the expansion of an existing building in the adjacent area. The site's characteristics, including limited manoeuvring space and a particularly sensitive surrounding environment, required careful planning and the use of specialised technologies.

The operations were carried out using Brokk 70 and Brokk 110 remote-controlled demolition robots, equipped with hydraulic breakers for rock fragmentation and buckets for handling the resulting material. Over approximately two weeks, 50 m³ of rock were demolished, ensuring precision, safety and operational efficiency even in the most difficult-to-access areas, while meeting the planned schedule.

2

Weeks | Time of realization

50

m³ of rock